Road Construction Updates

Road Construction Updates
Posted on 07/17/2026
Aerial view of a road and intersection in Aurora

As the city of Aurora improves its infrastructure offerings to its current and future residents, demands for more infrastructure, improvements and repairs also grow. On any given work day, there can be as many as 100 active work zones within the city.

Traffic engineering staff make every effort to minimize the impact of these work zones to the traveling public. In addition to reviewing and approving the plans to ensure they are safe and compliant with all regulations, staff also work with contractors to seek alternatives to street closures and minimize the number of lane closures and their duration. Staff also try to keep conflicting work zones from overlapping in time or space. In most cases, these efforts are successful. However, on occasion, alternatives are not available and since we are dealing with the outdoor environment, even the best planned projects get delayed by weather, special events or unknown conditions, resulting in confusion and/or unplanned congestion.

Sign up now for weekly construction updates delivered directly to your inbox via Road Construction Roundup.

Interactive map available
The city has an online map that shows work happening throughout the city that may impact travel on roadways. The map captures annual street maintenance work, transportation projects, public and private utility work, and development projects impacting roadways. Visit this link to view the map.


Annual Street Maintenance Work

See the Weekly Roadwork Construction Schedule

Visit this link
 for more information about city of Aurora roadwork.


Other Road Construction Work (weather delays may be expected for all work zones) 

Please note: Although the city informs online mapping services about our road closures and designated detours/alternate routes, the routes they provide to the general traveling public are generally the shortest or quickest routes between two points. That results in drivers sometimes not following the city's designated detour/alternate routes.

In-progress and due-to-start Projects

38th Avenue lane closure
Both directions of 38th Avenue between Tower and Himalaya roads will have one lane closed from 8:30 a.m. to 3:30 p.m. weekdays only through Sept. 4 due to a city project to improve medians.

64th Avenue lane closures
Both directions of 64th Avenue on both sides of Jackson Gap Street will have intermittent lane closures from 8:30 a.m. to 3:30 p.m. weekdays only from July 13 to Aug. 31 due to a city project to install new infrastructure.

Airport Boulevard lane closure (between Sixth and Centretech)
Both directions of Airport Boulevard between Sixth Avenue and Centretech Parkway will have one lane closed from 8:30 a.m. to 3:30 p.m. weekdays only through Sept. 4 due to a city project to improve medians.

Airport Boulevard lane closures (approaching 40th)
Northbound Airport Boulevard approaching 40th Avenue will have two lanes closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only from July 29 to Aug. 11 due to a private utility working to maintain utilities.

Aurora Parkway lane closures
Northbound Aurora Parkway north of Orchard Road will have two lanes closed from 8:30 a.m. to 3:30 p.m. weekdays July 13 to 31 due to a private utility working to install new utilities.

Center full closure at Nome
Both directions of Center Avenue between Nome and Peoria streets will be fully closed from 8:30 a.m. to 3:30 p.m. daily through Aug. 30 due to a city project to maintain infrastructure. The alternate route uses Exposition between Nome and Oswego. Plan for delays.

Chambers lane closure (at Hampden)
Southbound Chambers Road south of Hampden Avenue will have one lane closed 8:30 a.m. to 3:30 p.m. weekdays only through Feb. 10, 2027, due to a city project to replace sidewalk infrastructure.

Colfax BRT Project: Colfax and Havana lane closures
Both directions of Colfax Avenue at Havana Street will have lane closures around the clock through Aug. 14 due to the installation of new infrastructure related to the East Colfax Bus Rapid Transit Project.

Denali full closure
Both directions of Denali Boulevard between 47th and 49th avenues will have a full closure around the clock through Sept. 9 due to a private developer working to install new infrastructure.

Dunkirk lane closure
Both directions of Dunkirk between Jewell and Louisiana avenues will have one lane closed from 8:30 a.m. to 3:30 p.m. weekdays only from July 27 to Aug. 12.
 
Gartrell lane shift
Both directions of Gartrell Road between Aurora Parkway and East Dry Creek Road will have one lane shifted left around the clock through July 2027 due to a city project constructing enhanced traffic flow.
 
Gun Club lane closure
Eastbound Gun Club Road between East 10th and East 14th avenues will have one lane closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only from July 27 to Aug. 7 due to a private project to install new infrastructure.

Gun Club lane closure (at Sixth Avenue)
Both directions of Gun Club Road at Sixth Avenue will have intermittent lane closures from 8:30 a.m. to 3:30 p.m. July 20 to 24 due to a private utility working to maintain infrastructure.

Harvest lane closure
Northbound Harvest Road approaching Belleview Avenue will have one lane closed to through traffic around the clock from July 23 to 26 due to work to avoid any potential safety hazards.

Hoffman lane closures
Both directions of Hoffman Boulevard between Del Mar Circle and Yuba Street will have intermittent lane closures rolling several blocks at a time from 7 a.m. to 5 p.m. daily through Aug. 30 due to a city project to maintain infrastructure. Use alternate route; expect slow traffic.

Iliff Avenue lane closures
Both directions of Iliff Avenue between Buckley and Telluride roads will have one lane closed from 8:30 a.m. to 3:30 p.m. weekdays only through Sept. 4 due to a city project to improve medians.

Jackson Gap Street lane closures
Both directions of Jackson Gap Street on both sides of 64th Avenue will have intermittent lane closures from 8:30 a.m. to 3:30 p.m. weekdays only July 17 to Aug. 31 due to a city project to install infrastructure.

Jackson Gap turn lane closure
Southbound Jackson Gap Street approaching 56th Avenue will have a right turn lane closed from 8:30 a.m. to 3:30 p.m. July 23 due to a private project conducting potholing.

Lewiston lane closures
Both directions of Lewiston Way north of East Arapahoe Road will have intermittent lanes closed from 8:30 a.m. to 3:30 p.m. July 23 due to a private utility working to install new utilities.

Mississippi lane closures
Both directions of Mississippi Avenue at Havana Street will have intermittent lanes closed from 8:30 a.m. to 3:30 p.m. weekdays only from July 27 to Oct. 2 due to a private utility working to install new utilities.
 
Orchard Road lane closures
Westbound Orchard Road approaching Aurora Parkway will have intermittent lane closures from 8:30 a.m. to 3:30 p.m. weekdays only from July 17 to Aug. 14 due to a private utility working to install new utilities.

Peoria (approaching Mississippi) lane closures
Northbound Peoria Street approaching Mississippi Avenue will have two lanes closed to through traffic around the clock July 31 due to a private utility working to make emergency repairs.

Picadilly (at Sixth) lane closures
Both directions of Picadilly Road at Sixth Avenue will have intermittent lanes closed from 8:30 a.m. to 3:30 p.m. weekdays only from July 20 to 24 due to a private utility working to maintain infrastructure.

Plymouth lane closures
Both directions of Plymouth Drive between Ontario Drive and Ottawa Avenue will have intermittent lanes closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only from Aug. 3 to 14 due to a private utility conducting potholing.
 
Potomac lane closures (north of Sixth)
Both directions of Potomac Street north of Sixth Avenue will have alternating lanes closed from 8:30 a.m. to 3:30 p.m. weekdays only through Aug. 21 due to a private utility working to maintain utilities.

Quincy lane closure
Both directions of Quincy Avenue on both sides of Smoky Hill Road will have one lane closed to through traffic from 8:30 a.m. to 3:30 p.m. July 27 to 31 due to a private utility working to install new utilities.

Quincy lane closure
Westbound Quincy Avenue approaching Parker Road will have alternating lanes closed from 8:30 a.m. to 3:30 p.m. weekdays only through July 24 due to a city project to install new infrastructure.

Sixth Avenue lane closure (approaching Airport)
Eastbound Sixth Avenue approaching Airport Boulevard will have one lane closed 8:30 a.m. to 3:30 p.m. weekdays through Aug. 1 due to a city project to maintain infrastructure.

Sixth Avenue lane closure (between Chambers and Airport)
Both directions of Sixth Avenue between Chambers Road and Airport Boulevard will have one lane closed from 8:30 a.m. to 3:30 p.m. weekdays only from Aug. 3 to Sept. 4 due to a city project working to improve medians.

Salida lane closures
Northbound Salida Street approaching 40th Avenue will have two lanes closed to through traffic from 8:30 a.m. to 3:30 p.m. weekdays only from July 20 to Aug. 14 due to a private utility working to maintain utilities.

Smith Road full closure
Both directions of Smith Road between Gun Club Road and Powhaton Road will be fully closed around the clock through July 31 due to a private developer installing new infrastructure. Follow the signed detour route. 

Tower through lanes closed
Both directions of Tower Road at Smith Road will have through lanes closed weekdays only from 8:30 a.m. to 3:30 p.m. through Aug. 27 due to work to maintain utilities.

Warren lane closures
Both directions of Warren Avenue approaching Harvest Road will have intermittent lanes closed from 8:30 a.m. to 3:30 p.m. weekdays only from July 23 to Aug. 25 due to a private utility working to maintain utilities.


Parker/Quincy/Smoky Hill Intersection Improvements Project

Construction of the Parker/Quincy/Smoky Hill Intersection Improvement Project has begun and will continue through at least December 2026, with additional time built in to ensure the project is completed safely and successfully.

Construction activity will start at 7:30 a.m. and end at 5:30 p.m. Monday through Friday, with lane closures from 8:30 a.m. to 3:30 p.m.

Travel Impacts for Monday, July 20, to Friday, July 24 (lane closures will not occur simultaneously)

  • Southbound right lane closure on Parker Road just south of Quincy and continuing to just south of Rice Place.
  • Westbound right lane closure on Quincy Avenue from Atchison Way to Parker Road 24/7.
  • Eastbound right lane closure on Quincy Avenue from Parker Road to Smoky Hill Road.
  • Northbound right lane closure on Parker Road from Rice Place to Quincy Avenue.
Project update: 


Southbound Parker Road (West Side Trail):
The pedestrian handrail installation has been completed along the west-side trail on southbound Parker Road.

Northbound Parker Road (Rice Street to Quincy Avenue):
Sidewalk installation has been completed along the northbound side of Parker Road adjacent to the Starbucks shopping center (Rice Street area).
The remaining sidewalk section is scheduled to be placed this Friday, completing the connection between the newly constructed northbound sidewalk and the existing sidewalk at Quincy Avenue.

Overall, the project continues to progress as scheduled, with pedestrian improvements nearing completion along the Parker Road corridor. Once the final sidewalk section is poured, the continuous pedestrian path 

Visit the project webpage to view weekly travel impacts.


56th and Hudson Road Closures and Project

(view map for aerial view of closure impacts and alternate routes)

Please note: Flood damage has restricted access to both 56th Avenue and Hudson Road. Heavy rainfall undermined the roadways and destroyed the road surface in some locations. The road closures are necessary to protect the traveling public while the project team works to reopen the roadways. Project information will continue to be posted on the project webpage as it becomes available.

-56th Avenue between Monaghan and Hudson
Both directions of 56th Avenue between Monaghan and Hudson roads are fully closed around the clock due to extensive road damage. The replacement road is currently being designed, and construction is now estimated to start in late fall 2026. Follow the signed detour; use alternate routes. The detour route uses Monaghan Road or Imboden Road between 26th Avenue and 56th Avenue.
-Hudson Road between 56th Avenue and 26th Avenue
Both directions of Hudson Road between 56th and 26th avenues are fully closed around the clock due to extensive road damage. The replacement road is currently being designed, and construction is now estimated to start in late fall 2026. Follow the signed detour; use alternate routes. The detour route will use Monaghan Road or Imboden Road between 26th and 56th avenues.


I-70 Picadilly Interchange now open

The city of Aurora’s new diverging diamond interchange (DDI) at I-70 and Picadilly Road is now open to all lanes of travel in all directions for vehicle traffic. The newly constructed Picadilly Road from East 19th Avenue to Smith Road is also open, along with the new bike and pedestrian pathways. 

As you drive through the interchange, please pay attention to new overhead signs, as on- and off-ramp descriptions may have changed. 
 
Continuing Traffic Impacts
-Intermittent lane closures in the DDI may be required later this summer for final construction activities.

For more information on this project, visit the project webpage.


CDOT Road Construction Updates

View weekly construction updates from the Colorado Department of Transportation. 

Americans with Disability Act (ADA) improvement project begins on Colorado Highway 83 in early April

The Colorado Department of Transportation and prime contractor Chatos Concrete LLC, began an ADA sidewalk and curb ramp improvement project in April along Colorado Highway 83 (Parker Road). Work is taking place at over 25 intersection locations between East Florida and East Quincy Avenue, Mile Points 68.8 to 74. The project is expected to be completed by July 2026.

Work will consist of removing and replacing concrete sidewalks and curb ramps at intersections throughout the project corridor, focusing on over 100 ramps that require upgrades to meet Americans with Disabilities Act (ADA) standards. Additional operations will include minor signage improvements, striping work, and push button enhancements.

Visit the project webpage for more information.

Travel Impacts
-Daytime work hours range from 7 a.m. to 7 p.m., Monday through Friday with additional work expected most Saturdays
-Nighttime work may be required intermittently throughout the project
-Lane closure times will vary depending on the location and direction of the highway
-Motorists can anticipate various single-lane and shoulder closures throughout the project corridor. All lane closures will be concentrated around intersection locations\
-East and westbound roads that intersect with CO 83 within the work zone may experience minor travel impacts
-Partial closures at the on and off-ramps of CO 83 and I-225 are expected intermittently. Though full ramp closures and detour routes are not anticipated, they may be required
-Sidewalk and crosswalk access will remain open for the duration of the project. Partial closures will be marked with signage to navigate around active construction areas
-Visit COTrip.org for real-time lane closure updates and road conditions on this project and others throughout the state.


ARTA I-70 Aerotropolis Parkway Interchange Project

The Aerotropolis Regional Transportation Authority and contract partner, Ames Construction, is constructing the I-70 Aerotropolis Parkway Interchange in Adams County.

Part of ARTA’s planned regional transportation infrastructure improvements across the district, the purpose of the project is to provide much-needed access to developments from Aurora and Adams County, and to improve connectivity to Denver International Airport and the adjacent area served by the Aerotropolis Regional Transportation Authority.

Visit the ARTA website for schedule and working hours and ongoing traffic impacts. For questions, call the project hotline at 720.388.2660 or email [email protected].


E-470 Road Widening Updates

View more on this project from the E-470 Tollway Authority.


East Colfax Bus Rapid Transit coming to Aurora

East Colfax BRT Construction is now extending into Aurora, from Yosemite to I-225:
Construction will be completed in a single phase, with work occurring simultaneously at both eastbound and westbound stations.
Traffic control cones and lane closures will be used in active construction zones as work progresses.
Traffic will remain open in the center lanes of East Colfax Ave. throughout the project.
Work will progress block by block, with each section expected to take about 3 to 6 months to complete.
Construction work for the side-running stations will occur within designated work zones that include portions of the sidewalk.

In progress:

Both directions of Colfax Avenue at Havana Street will have lane closures around the clock through Aug. 31 due to the installation of new infrastructure related to the East Colfax Bus Rapid Transit Project.

Download this construction notice to find out more.

The BRT project continues the work started in Denver to replace the existing 15 and 15L buses and save bus riders up to 30 minutes in travel time from Union Station to the R Line Station at I-225.

Watch the Colfax BRT series, Col-FAQS: On the Street.

More information—including a small business toolkit with resources for how to thrive during construction—is available at DenverGov.org/ColfaxBRT. Business owners also may take a self-assessment to consider how your business might be impacted by construction and what you may need to do to prepare. Additional resources are available from the Aurora South Metro Small Business Development Center (SBDC) at AuroraGov.org/SBDC.
 

TRAFFIC: Due to unforeseen circumstances, detours will remain in place on n-bound Gun Club Rd through the pm rush hour & into the evening for work at this site. We'll also need to continue work tmrrow, so detours will be in effect from 8:30am-mid afternoon.

TRAFFIC: Due to unforeseen circumstances, detours will remain in place on n-bound Gun Club Rd through the pm rush hour & into the evening for work at this site. We'll also need to continue work tmrrow, so detours will be in effect from 8:30am-mid afternoon.

City of Aurora | All Rights Reserved | Powered by CivicLive | © 2026 Civiclive.