Schedule
Dates listed below are approximate and subject to change. Project milestones include:
- Existing Conditions (environmental and utilities): Completed in mid-2020
- Preliminary (30%) Design Plans Submittal: Completed in mid-2021
- Environmental Documentation: Early 2022
- Right-of-way and Easement Coordination with Impacted Properties: Late 2022 through 2024
- Final Environmental Clearance: Late 2024
- Final Design: Late 2024
- Construction Begins: Summer 2025
- Expected Construction Completion: Summer 2026
Project Funding
The city secured full funding for environmental study, design and construction of the planned operational improvements using city funds and federal funding administered by CDOT and the Denver Regional Council of Governments (DRCOG).
Contact the Project Team
The city of Aurora values concerns and comments of residents and businesses in the area. The 2016 study included extensive public involvement which shaped the plan for improvements. Please email or call Leah Langerman if you have any questions or would like to sign up to receive project updates.
Project Contact
Leah Langerman, Consultant Public Involvement Coordinator
720.225.4651 | [email protected]