Planning and Business Development Application Review Timelines
| Review Process |
Schedule 1 |
Schedule 2 |
Schedule 3 |
Schedule 3x |
|
Minor Site Plan
Amendments,
Conditional Use
Approvals; Cellular
installations; Sign
Variances
|
Site Plans and
Amendments;
Redevelopment
Plans; Plats;
Street Vacations,
Zonings, &
Neighborhood Plans
|
Zonings under 50
acres in conjunction
with any categories
1 or 2 application
types
|
All FDPs or Master Plans,
zonings over 50 acres |
| 1st City Review |
15 days |
15 days |
15 days |
20 days |
| 2nd City Review |
|
15 days |
15 days |
20days |
| Other Processing Tasks |
12 days |
12 days |
12 days |
15 days |
| 3rd City Review |
|
|
15 days |
20 days |
| Total working days |
27 days |
42 days |
57 days |
75 days |
| Total weeks |
5.4 weeks |
8.4 weeks |
11.4 weeks |
15 weeks |
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.
Civil Construction Plan Review Timelines
| Civil Construction Plans |
1-20 sheets |
21-50 sheets |
51-100 sheets |
101-200 sheets |
201-350 sheets |
351 plus |
| Pre acceptance |
City will complete pre-acceptance check. Incomplete submittals will be rejected. |
| First Submittal Review |
10 days |
20 days |
25 days |
35 days |
45 days |
55 days |
| Subsequent Submittal Review |
10 days |
15 days |
20 days |
25 days |
30 days |
40 days |
| Subsequent Submittal Review* |
10 days |
15 days |
20 days |
25 days |
30 days |
30 days |
| Signature Submittal Processing |
7 days |
7 days |
7 days |
10 days |
10 days |
10 days |
Subsequent Submittal Notes:
Most submittals will require three rounds of review prior to signature set.
Revision sets; up to 10-sheets including new sheets, 1-week signature set. Otherwise full review process defined by sheet #'s. Full review applies if drainage report is needed.
*Subsequent review prior to signature set if needed.
**Design Changes will require additional submittals.
***Unaddressed comments will require additional submittals.
****Any changes to plans identified at the time of signature set will be rejected and submittal process will start over.
Building Plan Review Timelines
| Building Plan Review |
Tenant Finish |
Limited |
Single Family
Residential |
Commercial
& Multi-Family |
| City Review for Code Compliance |
3 days |
7 days |
21 days |
26 days |
| City Review of Code Corrections |
1 day |
2 days |
2 days |
2 days |
| Total working days |
4 days |
9 days |
23 days |
28 days |
| Total weeks |
< 1 week |
1+ weeks |
4+ weeks |
5+ weeks |
Note: Building Permits cannot be issued until all other Development Review processes have been completed.
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.
Irrigation Construction Plan Review Timelines
| Irrigation Construction Plans |
Up to 5 sheets |
Up to 10 sheets |
11+ Sheets |
| 1st City Review |
10 days |
15 days |
20 days |
| 2nd City Review |
10 days |
10 days |
10 days |
| 3rd City Review |
5 days |
5 days |
5 days |
| Total working days |
25 days |
30 days |
35 days |
| Total weeks |
5 weeks |
6 weeks |
7 weeks |
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.