Planning and Business Development Application Review Timelines
Review Process |
Schedule 1 |
Schedule 2 |
Schedule 3 |
Schedule 3x |
|
Minor Site Plan
Amendments,
Conditional Use
Approvals; Cellular
installations; Sign
Variances
|
Site Plans and
Amendments;
Redevelopment
Plans; Plats;
Street Vacations,
Zonings, &
Neighborhood Plans
|
Zonings under 50
acres in conjunction
with any categories
1 or 2 application
types
|
All FDPs or Master Plans,
zonings over 50 acres |
1st City Review |
15 days |
15 days |
15 days |
20 days |
2nd City Review |
|
15 days |
15 days |
20days |
Other Processing Tasks |
12 days |
12 days |
12 days |
15 days |
3rd City Review |
|
|
15 days |
20 days |
Total working days |
27 days |
42 days |
57 days |
75 days |
Total weeks |
5.4 weeks |
8.4 weeks |
11.4 weeks |
15 weeks |
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.
Civil Construction Plan Review Timelines
Civil Construction Plans |
1-20 sheets |
21-50 sheets |
51-100 sheets |
101-200 sheets |
201-350 sheets |
351 plus |
Pre acceptance |
City will complete pre-acceptance check. Incomplete submittals will be rejected. |
First Submittal Review |
10 days |
20 days |
25 days |
35 days |
45 days |
55 days |
Subsequent Submittal Review |
10 days |
15 days |
20 days |
25 days |
30 days |
40 days |
Subsequent Submittal Review* |
10 days |
15 days |
20 days |
25 days |
30 days |
30 days |
Signature Submittal Processing |
7 days |
7 days |
7 days |
10 days |
10 days |
10 days |
Subsequent Submittal Notes:
Most submittals will require three rounds of review prior to signature set.
Revision sets; up to 10-sheets including new sheets, 1-week signature set. Otherwise full review process defined by sheet #'s. Full review applies if drainage report is needed.
*Subsequent review prior to signature set if needed.
**Design Changes will require additional submittals.
***Unaddressed comments will require additional submittals.
****Any changes to plans identified at the time of signature set will be rejected and submittal process will start over.
Building Plan Review Timelines
Building Plan Review |
Tenant Finish |
Limited |
Single Family
Residential |
Commercial
& Multi-Family |
City Review for Code Compliance |
3 days |
7 days |
21 days |
26 days |
City Review of Code Corrections |
1 day |
2 days |
2 days |
2 days |
Total working days |
4 days |
9 days |
23 days |
28 days |
Total weeks |
< 1 week |
1+ weeks |
4+ weeks |
5+ weeks |
Note: Building Permits cannot be issued until all other Development Review processes have been completed.
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.
Irrigation Construction Plan Review Timelines
Irrigation Construction Plans |
Up to 5 sheets |
Up to 10 sheets |
11+ Sheets |
1st City Review |
10 days |
15 days |
20 days |
2nd City Review |
10 days |
10 days |
10 days |
3rd City Review |
5 days |
5 days |
5 days |
Total working days |
25 days |
30 days |
35 days |
Total weeks |
5 weeks |
6 weeks |
7 weeks |
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.