Development Review Timelines

Planning and Business Development Application Review Timelines
Review Process Schedule 1 Schedule 2 Schedule 3  Schedule 3x

Minor Site Plan
Amendments,
Conditional Use
Approvals; Cellular
installations; Sign
Variances
Site Plans and
Amendments;
Redevelopment
Plans; Plats;
Street Vacations,
Zonings, &
Neighborhood Plans
Zonings under 50
acres in conjunction
with any categories
1 or 2 application
types
All FDPs or Master Plans,
zonings over 50 acres
1st City Review 15 days 15 days 15 days 20 days
2nd City Review
15 days 15 days 20days
Other Processing Tasks 12 days 12 days 12 days 15 days
3rd City Review

15 days 20 days
Total working days 27 days 42 days 57 days 75 days
Total weeks 5.4 weeks 8.4 weeks 11.4 weeks 15 weeks
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.


Civil Construction Plan Review Timelines
Civil Construction Plans 1-20 sheets 21-50 sheets 51-100 sheets 101-200 sheets 201-350 sheets   351 plus
Pre acceptance City will complete pre-acceptance check. Incomplete submittals will be rejected.
First Submittal Review  10 days 20 days  25 days 35 days 45 days 55 days
Subsequent Submittal Review 10 days  15 days 20 days 25 days 30 days 40 days
Subsequent Submittal Review* 10 days  15 days 20 days 25 days 30 days 30 days
Signature Submittal Processing 7 days 7 days 7 days 10 days 10 days 10 days
 Subsequent Submittal Notes:
 Most submittals will require three rounds of review prior to signature set.
 Revision sets; up to 10-sheets including new sheets, 1-week signature set. Otherwise full review process defined by sheet #'s. Full review applies if drainage report is needed.
 *Subsequent review prior to signature set if needed.
 **Design Changes will require additional submittals.
 ***Unaddressed comments will require additional submittals.
 ****Any changes to plans identified at the time of signature set will be rejected and submittal process will start over.


Building Plan Review Timelines
Building Plan Review Tenant Finish Limited Single Family
Residential
Commercial
& Multi-Family
City Review for Code Compliance 3 days 7 days 21 days 26 days
City Review of Code Corrections 1 day 2 days 2 days 2 days
Total working days 4 days 9 days 23 days 28 days
Total weeks < 1 week 1+ weeks 4+ weeks 5+ weeks
Note:  Building Permits cannot be issued until all other Development Review processes have been completed.
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.
 


Irrigation Construction Plan Review Timelines
Irrigation Construction Plans Up to 5 sheets Up to 10 sheets 11+ Sheets
1st City Review 10 days 15 days 20 days
2nd City Review 10 days 10 days 10 days
3rd City Review 5 days 5 days 5 days
Total working days 25 days 30 days 35 days
Total weeks 5 weeks 6 weeks 7 weeks
*Please note that these are city timelines, and they do not factor in the time it takes for consultants to address any necessary corrections.