Lima and Wesley Sidewalk Widening-Archived

The Lima Street Sidewalk Widening Project is about to be in the construction phase, and is anticipated to widen some sidewalks in the Eastridge neighborhood. This project is the result of an Americans with Disabilities Act (ADA) accommodation request from a resident in the area.
 
The project scope includes widening the sidewalks on the north side of South Lima Street from approximately 3 feet in width to 6 feet in width between East Wesley Place and East Wesley Avenue. The sidewalks will also be widened on the north side of East Wesley Avenue between South Lima Street to Eastridge Elementary School. There are also anticipated design improvements to the pedestrian crossings at the intersection of South Lima Street and East Wesley Avenue.

Public Meetings

Two public meetings have taken place for this project. Documents from these meetings can be found on this website.

Public Meeting No. 1: Sept. 24, 2019
Held in person at Eastridge Community Elementary School

Preferred Alternative Roll Plot
Preferred Alternative Considerations

Alternative 2 Roll Plot
Alternative 2 Considerations

Public Meeting No. 2: March 1, 2022
Virtual meeting

Virtual Meeting Presentation
Updated Roll Plot

Project Schedule

  • Project scoping – Finished 2019
  • Preliminary design: 2019-2020
  • Final Design: 2020-2022
  • Easement acquisition: completed in 2022
    • Impacted property owners were provided with specific information for their properties and acquisition paperwork has been signed
  • Construction: 2023 (Spring/Summer)
    • Contract was awarded to Goodland Construction
    • Work should start by the end of April, pending weather
    • Work will be completed by September 2023

Contact Information

Rocky Carns
Consultant Project Construction Engineer/Inspector
JR Engineering
[email protected]

Carlie Campuzano, PE, PTOE
Aurora Traffic Manager
[email protected]